Ofgem sends back BSC modification P441 and REC change R0268 for further work, pushing complex site classes decision to 5 October 2026
Ofgem has returned BSC modification P441 and its REC counterpart R0268 to industry for further work, delaying a decision on complex site classes until 5 October 2026.

Ofgem has issued send-back decision letters for BSC modification P441 - "Creation of Complex Site Classes" - and its Retail Energy Code counterpart R0268, returning both proposals to industry for additional work[1]. The regulator's timetable now lists 5 October 2026 as the target decision date for both modifications, a delay of several months from the June 2026 implementation window that had been anticipated when P441 was formally submitted to the Authority on 19 March 2026[1].
What P441 proposes
P441 seeks to formalise the concept of Complex Sites - metering arrangements too intricate to be captured in standard BSC data flows - by codifying them into six defined classes[1]. The BSC Panel unanimously recommended approval at its meeting on 12 March 2026, and 22 responses to the report-phase consultation were received, with the majority in support.
The six classes break down as follows:
- Classes 1-4: codify criteria for existing standard complex site arrangements already in use across the industry
- Class 5: permits netting of imports and exports at separate boundary points for local energy schemes operating under a supply licence exemption
- Class 6: captures non-standard arrangements not covered by Classes 1-5, subject to BSC Panel approval on a case-by-case basis
Class 5 carries the most commercial weight. Because netting reduces net import volumes, participants would be exempt from Balancing Services Use of System (BSUoS) charges on the netted portion - a material cost saving that Ofgem has flagged as requiring careful analysis before it can be locked into the code.
Why Ofgem sent it back
The send-back is consistent with a pattern of extended scrutiny on P441. Ofgem first signalled the need for further analysis at the eighth workgroup meeting in September 2023, prompting a six-month assessment extension that October. Subsequent extensions followed in April 2024 and again in 2025, with the BSC Panel granting a 21-month extension at its July 2025 meeting to allow CEPA to complete a two-phase cost-benefit analysis.
The outstanding concern centres on whether the BSUoS exemption available to Class 5 participants is justified by wider network benefits - or whether it simply shifts costs onto non-participating consumers. Elexon has indicated that a post-implementation review mechanism would assess this after go-live, but Ofgem has not yet accepted that as sufficient assurance.
R0268 is a consequential cross-code change in the Retail Energy Code that mirrors P441's metering and data-flow requirements. Because it cannot proceed independently of the BSC modification, it is sent back on the same timeline.
What to watch
The 5 October 2026 decision date gives Elexon and the REC Company roughly eight weeks to address Ofgem's outstanding concerns and resubmit. The key question is whether the CEPA modelling - described as concluding "over summer" in the July 2026 BSC Change Report - will be complete and accepted by the Authority in time. Community energy schemes and local supply operators that have been waiting on P441 to formalise their metering arrangements face continued uncertainty in the interim. A further send-back or extension beyond October would push implementation into 2027.
The images and texts on this page were created with the help of AI.
Related
RenewablesSwitzerland counts approximately 1,860 active local electricity communities six months after their legal introduction
A Swissolar survey of Switzerland's 30 largest DSOs found 1,323 active LECs at end-June 2026, extrapolating to roughly 1,860 nationwide - but regulatory barriers are slowing the rollout.
7 Sept 2026
RenewablesDong Fang Offshore launches Orient Trailblazer hull in Romania, delivery set for Q2 2027
Dong Fang Offshore's first newbuild offshore subsea construction vessel was launched at VARD's Brăila yard on 21 August. Delivery to Taiwan is scheduled for Q2 2027.
7 Sept 2026
RenewablesPerigus Energy names Tom O'Brien as independent chair four months after CIP acquisition
Perigus Energy has appointed Tom O'Brien, formerly of Brookfield Asset Management, as independent chair, alongside promotions to CCO and CFO at its Cork headquarters.
7 Sept 2026