OnPath Energy breaks ground at 49.9 MW Common Farm Solar Park in South Yorkshire, targeting mid-2027 completion
OnPath Energy has started construction at the 49.9 MW Common Farm Solar Park in Dinnington, South Yorkshire, with Spanish EPC contractor Grupotec on site and a mid-2027 completion target.

OnPath Energy has started construction at the Common Farm Solar Park near Dinnington, South Yorkshire - a 49.9 MW solar project co-located with a 50 MW battery storage facility, targeting completion in mid-2027[1]. Spanish engineering contractor Grupotec is on site, with piling, cable trenching, access roads, fencing, foundations, and drainage already under way.
What is being built
The Common Farm Solar Park will have an installed capacity of up to 49.9 MW, with a 50 MW battery storage facility linking directly into the Thurcroft electricity sub-station around three kilometres to the north of the site. The project sits on a 116-hectare site on the western approach to Dinnington, approximately two kilometres north-east of Junction 31 of the M1.
Key project parameters:
- Solar capacity: 49.9 MW
- Co-located BESS: 50 MW, connecting to Thurcroft sub-station
- Site area: 116 hectares
- Projected output: enough to meet the average annual electricity needs of up to 18,800 homes
- Community benefit fund: £50,000 over the lifespan of the site
OnPath has brought in specialist engineering contractor Grupotec to work on the development, which is scheduled to be completed by mid-2027. Work so far has been on piling, cable trenching, access roads, and fencing for the solar farm, and foundations and drainage have been put in place. Grupotec will carry out operational maintenance and management work for the first two years after generation begins.
Grid connection and consultancy
The project's 50 MW battery storage facility will link directly into the Thurcroft electricity sub-station to help make the energy grid more efficient. TMS Grid has started work on levelling and preparing the 2,500 square metre substation site, with construction of the building expected to start around the end of the year. AECOM is acting as lead infrastructure consultant across the scheme.
Offtake structure
SmartestEnergy and OnPath Energy have signed a co-location agreement for the Common Farm Solar Park, combining solar PV generation with battery energy storage in a single integrated project. Scheduled to begin operations in 2027, the development marks SmartestEnergy's first co-located solar and battery project and OnPath Energy's first hybrid solar-plus-storage project in the UK. A key feature of the agreement is a revenue floor mechanism, which provides developers with greater income certainty while still allowing them to benefit from favourable market conditions.
Co-location is playing an increasingly important role in how the market evolves, particularly as grid capacity becomes more constrained, according to SmartestEnergy's trading team.
Development path
Rotherham Metropolitan Borough Council voted in favour of the project, with a majority of eight votes to one, in May 2023. OnPath Energy, formerly known as Banks Renewables, submitted planning in 2022. The project has since moved through site access construction, substation preparation, and ecological groundwork - including species-rich grassland planted across the full 116 hectares - before reaching the main construction phase.
Common Farm is one of two solar energy projects currently being developed in Yorkshire by OnPath Energy, with work already underway at the Barnsdale Solar Energy Park near Leeds, while it already owns and operates four onshore wind farms across the county.
The mid-2027 completion date is the figure to watch. Grupotec's two-year post-commissioning O&M commitment means the contractor's performance through the build phase will carry direct consequences for early operational revenue - and for how the SmartestEnergy revenue floor mechanism is tested in practice.
The images and texts on this page were created with the help of AI.
Related
Markets & PolicyNorth Carolina rooftop solar leasing window narrows as Section 48E safe harbor closes
NC rooftop solar fell two-thirds in Q1 2026 after the 25D credit expired. Leasing companies are filling the gap - but the Section 48E safe harbor closed 4 July, tightening the runway to end-2027.
12 Aug 2026
Markets & PolicyIllinois coal-to-solar initiative delivered three small farms and no stand-alone storage, new report finds
A University of Illinois and Prairie Rivers Network report finds Illinois' Coal to Solar and Energy Storage Initiative produced far less than planned, pointing to a $30 REC price, coal ash, and site constraints as the main culprits.
12 Aug 2026
StorageCIP closes $510 million financing for 750 MWh solar-plus-storage project in Mexico's Campeche state
Copenhagen Infrastructure Partners reached financial close on 6 August on La Esperanza Solar, a 420 MWdc / 750 MWh project in Campeche - its first Mexico investment to clear financing.
12 Aug 2026