Beltline Energy withdraws $16 billion data center rezoning application in Pacific, Missouri, two days after city passes 12-month moratorium
Atlanta-based Beltline Energy has pulled its rezoning application for a $16 billion, 500-acre data center in Pacific, Missouri, days after the city enacted a 12-month moratorium and following a Franklin County P&Z denial.

Atlanta-based Beltline Energy formally withdrew its rezoning application for a proposed $16 billion data center campus in Pacific, Missouri, on 7 August 2026[1], two days after the Pacific Board of Aldermen passed a 12-month moratorium barring acceptance of any new data center applications[1]. The withdrawal was communicated by BLE Landholdings, a subsidiary of Beltline Energy, via email to city officials[1].
What was proposed
Beltline, an Atlanta-based developer focused on energy development and digital infrastructure, wanted to build a data center on a 500-acre site along Highway O at Phelan Road, just south of Pacific. The project would have cost an estimated $16 billion. According to Beltline's own description, the Meramec Valley Technology Park would have comprised sixteen buildings and added 200 MW of load annually, ultimately employing 30 to 40 people at an average salary of $120,000 a year.
The site presented a complicating factor from the outset: the acreage in question was not even in the city yet, meaning any development would have required annexation before rezoning could proceed.
A year of opposition and procedural setbacks
Community resistance began in January 2026, when residents packed a Board of Aldermen meeting to oppose the plan. A report completed by the Missouri Department of Conservation noted the project's footprint includes habitats for endangered species of bats, salamanders, and others, and the department requested opportunities to collaborate on technical advice to protect fish, forest, and wildlife in the area.
In February 2026, Beltline pulled its request from a Planning and Zoning Commission agenda, citing an inability to finalize a funding agreement. The developer then shifted its application to Franklin County, where the Franklin County Planning and Zoning Commission voted to deny the rezoning request in late April 2026, following local opposition over environmental impacts.
With the county route closed, the application reverted to Pacific. The Pacific City Council passed a 12-month stay of acceptance for any new data center proposals on 5 August 2026, providing time for the city to conduct a land-use study, gather more community feedback, and make any necessary updates to its comprehensive plan or zoning texts. Notably, the Beltline application was not subject to the recently passed stay, meaning the council could still have approved the plan - making the subsequent withdrawal a voluntary exit rather than a forced one.
The broader moratorium wave
Pacific's action is one of dozens of similar local measures enacted across the United States in 2026. New one-year or longer pauses have taken effect in Seattle, Spokane, Broomfield (Colorado), Prince George's County (Maryland), and Sarasota County (Florida), while Jackson County and Springfield, Missouri, among other jurisdictions, have also adopted new pauses. New York's legislature passed the first-in-the-nation statewide measure, the Responsible Data Center Development Act, on 4 June 2026, imposing a one-year moratorium on new permits for large data centers of 20 MW or more.
The pattern in Pacific mirrors what has played out in other markets. Stillwater Development withdrew a 1.25 GW application in Lovejoy, Georgia, in August 2026 after sustained community opposition, and AWS pulled a 500 MW campus application adjacent to Calvert Cliffs in Maryland following a county primary that ousted commissioners who had opposed a development pause.
What to watch
Opponents in Pacific say the fight now shifts to Franklin County, where Dallas-based Provident Data Centers is targeting 613 acres near Gray Summit, with the Franklin County P&Z having recommended approval in a split vote. The Franklin County Commission has yet to issue a final ruling on that application. Pacific's 12-month moratorium also leaves open the question of what land-use framework the city will adopt before the stay expires - and whether any developer will return under different terms.
The images and texts on this page were created with the help of AI.
Related
NRC's July transport rule modernizes shielding limits but leaves HALEU criticality problem unsolved
The NRC's 27 July proposed rule eases Type B package radiation limits for irradiated microreactors. It does not touch the harder constraint blocking commercial HALEU fuel shipments: criticality safety.
13 Aug 2026Blue Energy pairs gas turbines with BWRX-300 reactors in a bid to make nuclear project-financeable for the first time
Blue Energy's gas-to-nuclear strategy - prefabricated shipyard modules, fixed-price contracts, and early gas revenue - aims to unlock commercial project debt for nuclear, a first in the sector's history.
13 Aug 2026
GridEvergy signs 3 GW of large-load agreements and files a 5 GW generation plan to match
Evergy has executed electric service agreements covering 3 GW of large-load demand and filed IRPs calling for more than 5 GW of new generation through 2032, with 1-2 GW more in advanced talks.
13 Aug 2026